claude-skills-reference/project-management/senior-pm/assets/raci_matrix_template.md
Leo 882ce5abd1 feat(pm): elevate scrum-master and senior-pm to POWERFUL tier
- scrum-master: add velocity_analyzer, sprint_health_scorer, retrospective_analyzer
- scrum-master: add references, assets, templates, rewrite SKILL.md
- senior-pm: add risk_matrix_analyzer, resource_capacity_planner, project_health_dashboard
- senior-pm: add references, assets, templates, rewrite SKILL.md
- All scripts: zero deps, dual output, type hints, tested against sample data
2026-02-15 20:36:56 +00:00

11 KiB

RACI Matrix Template

Project: [Project Name]
Version: [Version Number]
Date: [Creation/Update Date]
Owner: [Project Manager Name]


RACI Matrix Legend

Code Role Description
R Responsible The person(s) who actually performs the work to complete the task
A Accountable The person who is ultimately answerable for the correct completion
C Consulted The person(s) whose opinions are sought and with whom there is two-way communication
I Informed The person(s) who are kept up-to-date on progress, often only one-way communication

RACI Best Practices

  • One A per activity - Only one person can be accountable for each task
  • At least one R per activity - Someone must be responsible for doing the work
  • Minimize C's - Too many consulted stakeholders can slow decision-making
  • Strategic I's only - Inform only those who truly need to know

Stakeholder Roster

Core Project Team

Name Role Department Contact Availability
[Name] Project Manager PMO [email] 100%
[Name] Product Owner Product [email] 75%
[Name] Technical Lead Engineering [email] 90%
[Name] UX Designer Design [email] 50%
[Name] QA Lead Quality [email] 60%

Executive Stakeholders

Name Role Department Contact Decision Authority
[Name] Executive Sponsor [Department] [email] Budget & Strategic Direction
[Name] Business Owner [Department] [email] Requirements & Acceptance
[Name] Technical Owner [Department] [email] Architecture & Standards

Extended Stakeholders

Name Role Department Contact Interest Level
[Name] [Role] [Department] [email] High/Medium/Low
[Name] [Role] [Department] [email] High/Medium/Low

Project Phase RACI Matrices

Phase 1: Project Initiation & Planning

Activity Project Manager Executive Sponsor Business Owner Product Owner Technical Lead
Business Case Development R A R C C
Project Charter Creation A, R A C C C
Stakeholder Analysis A, R C R C I
Initial Requirements Gathering A I R R C
High-Level Architecture A I C C R
Resource Planning A, R A C C C
Budget Approval R A C I I
Risk Assessment A, R C C C R
Project Charter Sign-off R A A C C

Phase 2: Design & Development Setup

Activity Project Manager Product Owner Technical Lead UX Designer QA Lead
Requirements Documentation A R C C C
Technical Architecture A C R I C
System Design Documentation A C R C C
UI/UX Design A R C R I
Database Design A I R I C
API Specifications A C R I C
Test Strategy A C C I R
Development Environment Setup A I R I C
CI/CD Pipeline Setup A I R I R

Phase 3: Development & Implementation

Activity Project Manager Product Owner Technical Lead Dev Team QA Lead
Sprint Planning R A R R C
User Story Development A R C C C
Code Development A C R R I
Code Reviews I I A R I
Unit Testing I I R R C
Integration Testing A C R R R
Feature Testing A R C I R
Bug Triage R A R R R
Sprint Reviews A, R R R R R

Phase 4: Testing & Quality Assurance

Activity Project Manager Product Owner Technical Lead QA Lead Business Owner
Test Plan Creation A C C R C
System Testing A C C R I
Performance Testing A C R R I
Security Testing A I R R I
User Acceptance Testing A R C C R
Bug Resolution A C R R I
Go-Live Readiness A R R R R
Sign-off Documentation R R C R A

Phase 5: Deployment & Launch

Activity Project Manager Technical Lead DevOps Business Owner Support Team
Deployment Planning A R R C C
Production Deployment A R R I I
Smoke Testing A R C C R
Go-Live Communication R C I A I
User Training A C I R C
Support Documentation A C C C R
Monitoring Setup A R R I R
Launch Retrospective A, R R C R C

Decision-Making RACI

Strategic Decisions

Decision Type Project Manager Executive Sponsor Business Owner Technical Owner
Budget Changes >10% R A C C
Scope Changes (Major) R A R C
Timeline Changes >2 weeks R A R C
Technology Platform Changes R C C A
Resource Reallocation A, R A C C
Go/No-Go Decisions R A R R

Operational Decisions

Decision Type Project Manager Product Owner Technical Lead Team Members
Sprint Scope C A R R
Technical Implementation C C A, R R
Bug Priority A R C C
Code Standards C C A, R R
Testing Approach A C R R
Daily Task Assignment I C A R

Escalation Paths & Conflict Resolution

Escalation Matrix

Issue Level Primary Resolver Escalation To Timeline Authority
Level 1: Task/Technical Team Member → Technical Lead Product Owner 24 hours Technical decisions
Level 2: Sprint/Feature Technical Lead → Product Owner Project Manager 48 hours Feature scope/priority
Level 3: Project Impact Project Manager → Business Owner Executive Sponsor 72 hours Budget/timeline changes
Level 4: Strategic Executive Sponsor → Steering Committee CEO/Board 1 week Strategic direction

Conflict Resolution Process

  1. Direct Resolution (Level 1)

    • Who: Conflicting parties attempt direct resolution
    • Timeline: 24 hours
    • Documentation: Brief note in project log
  2. Mediated Resolution (Level 2)

    • Who: Project Manager facilitates discussion
    • Timeline: 48 hours from escalation
    • Documentation: Decision recorded with rationale
  3. Executive Resolution (Level 3)

    • Who: Executive Sponsor makes binding decision
    • Timeline: 72 hours from escalation
    • Documentation: Formal decision memo to all stakeholders
  4. Steering Committee (Level 4)

    • Who: Full steering committee vote
    • Timeline: Next scheduled meeting (max 1 week)
    • Documentation: Board resolution or meeting minutes

Communication Protocols

  • Escalation Notification: All RACI stakeholders informed within 4 hours
  • Decision Communication: Decision communicated to all affected parties within 24 hours
  • Documentation: All escalations and resolutions logged in project management system

Communication & Meeting RACI

Regular Meetings

Meeting Type Frequency Project Manager Team Stakeholders Sponsor
Daily Standup Daily A R I I
Sprint Planning Bi-weekly A R C I
Sprint Review Bi-weekly R R A C
Stakeholder Updates Weekly A, R C R A
Steering Committee Monthly R I C A

Communication Artifacts

Artifact Creator (R) Approver (A) Reviewers (C) Recipients (I)
Status Reports Project Manager Business Owner Team Leads All Stakeholders
Risk Register Project Manager Executive Sponsor Risk Owners Steering Committee
Change Requests Requestor Business Owner Project Manager Affected Teams
Decision Log Project Manager Decision Maker Consulted Parties All Stakeholders

Risk & Issue Management RACI

Risk Management

Activity Project Manager Risk Owner Executive Sponsor Team
Risk Identification A R C R
Risk Assessment A R C C
Mitigation Planning A R C R
Risk Monitoring A R I C
Risk Escalation R R A I

Issue Resolution

Issue Severity Reporter (R) Owner (A) Resolver (R) Informed (I)
Critical Anyone Project Manager Technical Lead Executive Sponsor
High Team/Stakeholder Technical Lead Team Member Project Manager
Medium Team Member Team Lead Team Member Project Manager
Low Team Member Team Member Team Member Team Lead

RACI Validation & Maintenance

Validation Checklist

  • Every activity has exactly one "A" (Accountable)
  • Every activity has at least one "R" (Responsible)
  • "C" (Consulted) roles are minimized to essential stakeholders
  • "I" (Informed) includes only those who truly need updates
  • No person is assigned "A" for more tasks than they can handle
  • Escalation paths are clear and realistic
  • Decision rights match organizational authority

Review & Update Process

  • Review Frequency: Every project phase or monthly
  • Update Triggers: Team changes, scope changes, organizational changes
  • Approval Process: Changes require Project Manager and Executive Sponsor approval
  • Communication: RACI updates communicated to all stakeholders within 48 hours

RACI Health Metrics

Metric Target Current Notes
Decision Speed <48 hours [X] hours Average time for routine decisions
Escalation Rate <10% [X]% Percentage of issues requiring escalation
Role Clarity >90% [X]% Stakeholder survey on role understanding
Conflict Resolution <72 hours [X] hours Average resolution time

Document Control:

  • Version: [Version Number]
  • Last Updated: [Date]
  • Next Review: [Date]
  • Approved By: [Executive Sponsor Name]

Distribution List:

  • All Project Stakeholders (as identified in roster)
  • PMO (for template compliance)
  • HR (for role clarity and performance management)