Portfolio KPIs Reference

Delivery KPIs

KPI Formula Target
Sprint Velocity Story points completed / sprint Stable ±10%
Sprint Predictability Completed / Committed × 100 ≥80%
Cycle Time Time from In Progress → Done Decreasing trend
Lead Time Time from Created → Done <2 sprints
Throughput Items completed per sprint Increasing trend

Quality KPIs

KPI Formula Target
Defect Escape Rate Prod bugs / total stories × 100 <5%
Rework Rate Reopened items / completed × 100 <10%
Test Coverage Covered lines / total lines × 100 >80%

Team Health KPIs

KPI Formula Target
Planned vs Unplanned Unplanned work / total work × 100 <20%
Blocked Time Hours blocked / total hours × 100 <10%
WIP Limit Compliance Times WIP exceeded / sprints × 100 <15%

Portfolio KPIs

KPI Formula Target
On-Time Delivery Projects on schedule / total >85%
Budget Variance (Actual - Budget) / Budget × 100 ±10%
Resource Utilization Allocated / Available × 100 70-85%
Strategic Alignment Projects aligned to OKRs / total >80%